A Road on Paper, Potholes on the Ground

What the project progress report says did not match the measurements.

A Road on Paper, Potholes on the Ground

In the project documents the road is "92 percent complete". With a measuring tape and the help of a local engineer, we walked its entire length.

Over two kilometres had not been paved, and in places there were no culverts. The construction firm says the monsoon delayed the work.

Yet the project bill has already been released — this fact is our main question. Written questions have been sent to the department concerned.